With the Official Opening just a week away, the Trail surface in fine shape, and some signage in place, the Operations Committee, under the direction of Jim Paterson, continues to make improvements. Jim sent in this report:

This next phase includes the placement of rocks adjacent to each of the sets of bollards at various intersection locations between Lindsay and Omemee. This will further restrict access to the trail by motorized vehicles such as ATV’s. In addition, there are existing drainage problems on each side of the section of the trail just east of the Slanted Road. We are having some ditching work done on this section and also having a culvert installed to move the water away from this area of the trail. Once the ditching and culvert work is done we will have the trail re-graded.

You can check out photos taken by Bill Elliott in a gallery. One photo shows the old bridge just west of the hamlet of Reaboro. This bridge did not have any decking on it and was recently covered by our KTCT volunteer from Reaboro, Denis Grignon. Thanks Denis!

Sign up for our newsletter